AGENDA
KEY DATES AND MILESTONES
Overview of Upcoming Tasks - Actual dates are dependent on plan data passing validation
Cohort Baseline Finish Date
Owner
Task
11/06/2023
Plan
Confirm data files contain both, valid keys & Kyruus Health data analysis (Prerequisite Action 2)
11/28/2023
Approve data for updating UAT (Planning Action 1)
12/19/2023
Kyruus Health
Update plan specific provider intake configurations and carve out rules
Update plan specific BPDKEY preferences (allows for AXIS v9 & CLNR v3)
12/20/2023
Confirm Provider Data is available in Test Environment for each Client (Execution Action 1)
01/26/2024
Validation of Provider Demographics in the UI (Execution Action 2)
Validation of Downstream Processes in the UI (TCE/NCCT v9, TIC/CLNR v3, Reviews, etc.) (Execution Action 3)
Key Upcoming Milestones
Date
Milestones
BCBSA Milestone
End-to-End Testing Checkpoint Due
01/31/2024
Complete Final End-to-End (E2E) Testing
02/09/2024
PDT Executive Signoff
03/15/2024
Kyruus Health Production Cutover (move all BPDKEY configurations & functionality to each Plan's Production Environment)
Cutover