Agenda and Schedule Overview

Summary

Summary

AGENDA

  • SCHEDULE REVIEW & PROJECT STATUS
  • DATA VALIDATION
  • QUESTIONS AND ANSWERS
  • NEXT STEPS | HELPFUL INFORMATION

KEY DATES AND MILESTONES

Overview of Upcoming Tasks - Actual dates are dependent on plan data passing validation

Cohort Baseline Finish Date

Owner

Task

11/06/2023

Plan

Confirm data files contain both, valid keys & Kyruus Health data analysis (Prerequisite Action 2)

11/28/2023

Plan

Approve data for updating UAT (Planning Action 1)

12/19/2023

Kyruus Health

Update plan specific provider intake configurations and carve out rules

12/19/2023

Kyruus Health

Update plan specific BPDKEY preferences (allows for AXIS v9 & CLNR v3)

12/20/2023

Plan

Confirm Provider Data is available in Test Environment for each Client (Execution Action 1)

01/26/2024

Plan

Validation of Provider Demographics in the UI (Execution Action 2)

01/26/2024

Plan

Validation of Downstream Processes in the UI (TCE/NCCT v9, TIC/CLNR v3, Reviews, etc.) (Execution Action 3)

Key Upcoming Milestones

Date

Owner

Milestones

12/20/2023

BCBSA Milestone

End-to-End Testing Checkpoint Due

01/31/2024

BCBSA Milestone

Complete Final End-to-End (E2E) Testing

02/09/2024

BCBSA Milestone

PDT Executive Signoff

03/15/2024

Kyruus Health

Kyruus Health Production Cutover (move all BPDKEY configurations & functionality to each Plan's Production Environment)

03/15/2024

BCBSA Milestone

Cutover