Schedule Overview

Summary

Summary

Overview of Upcoming Tasks - Actual dates are dependent on plan data passing validation

Cohort Baseline Finish Date

Task

11/06/2023

Confirm data files contain both, valid keys & HealthSparq data analysis (Plan Deliverable) (Prerequisite Action 2)

11/28/2023

Approve data for updating UAT (Plan Deliverable) (Planning Action 1)

12/19/2023

Update plan specific provider intake configurations and carve out rules (HealthSparq Deliverable)

12/19/2023

Update plan specific BPDKEY preferences (allows for new NCCT & CLNR endpoints) (HealthSparq Deliverable)

12/20/2023

Confirm Provider Data is available in Test Environment for each Client (Plan Deliverable) (Execution Action 1)

01/26/2024

Validation of Provider Demographics in the UI (Plan Deliverable) (Execution Action 2)

01/26/2024

Validation of Downstream Processes in the UI (TCE/NCCT v9, TIC/CLNR v3, Reviews, etc.) (Plan Deliverable) (Execution Action 3)

KEY UPCOMING DATES

Date

Milestones

12/20/2023

BCBSA End-to-End Testing Checkpoint Due

01/31/2024

BCBSA Final E2E Testing Complete (Begins 11/15/2023)

02/01/2024

BCBSA Sign Off

03/15/2024

HealthSparq Production Cutover (move all BPDKEY configurations & functionality to each Plan's Production Environment)

03/15/2024

BCBSA Cutover