At this point in the cohort, plans should be confirming that provider data is available in the test environment, which is Execution Action 1.
Planning Action 1 - Analysis In-Process Tickets
Plan specific analysis continues
- Many plans submitted new files for analysis towards the end of the week
- Plans will receive current status by EOD today (12/28/2023)
- Status will be shared in Planning Action 1 ticket
- HealthSparq is analyzing new files
- Timing - baseline time is up to 2wks to perform the analysis
Next Steps
- Completed analysis reports are provided (HealthSparq Deliverable)
- Review the updated reports (Plan Deliverables)
- Determine if the reports can be approved or if new data and additional analysis is needed (Plan Deliverables)
- If analysis is approved, update configurations and preferences (HealthSparq deliverable)